Demolition and removal of selected portions of building or structure:

1. Remove existing PVC membrane and all PVC roof flashings
2. Existing Iso-board insulation to be left in place. Replacement of any unsuitable insulation will be processed via Change Order at agreed upon price.
3. Coping and gutter to remain.
4. Solar Panels to be removed by Others.

For information regarding this Invitation to Bid, contact as follow:

Cary Rodriguez
Senior Project Manager
Gaston County Public Works
P.O. Box 1578, Gastonia, NC 28053
Phone: 704-862-6791
Email:Cary.Rodriguez@gastongov.com

Bidders must be a licensed contractor in the State of North Carolina. Subject to the provisions of the State of North Carolina Contractor’s Licensing Law, it will be necessary for the contractor to place his contractor’s license number on the envelope containing his bid.

No bid shall be considered or accepted by Gaston County unless at the time of its filing the same shall be accompanied by a deposit of cash or certified check on some bank or trust company insured by the Federal Deposit Insurance Corporation in an amount equal to not less than five percent (5%) of the proposal. In lieu of making the cash deposit, bidder may file a bid bond executed by a corporate surety licensed under the laws of North Carolina to execute such bonds, conditioned that the surety will, upon demand forthwith make payment to the obligee upon said bond if the bidder fails to execute the contract in accordance with the bid bond. This deposit shall be retained if the successful bidder fails to execute the contract within ten (10) days after the award or fails to give satisfactory surety as required herein.

The successful bidder shall be required to enter into a contract with Gaston County in writing and shall be required to furnish bond from some surety company authorized to do business in the State of North Carolina, make deposit of money, certified check, or government sureties for the full amount of said contract for the faithful performance of the terms of said contract as required by Section 143-129 of the General Statutes of North Carolina.

No bid shall be withdrawn after the opening of bids without the consent of Gaston County, for a period of sixty (60) days after the scheduled time of closing bids. The Bid securities of all bidders, except those submitted with the three (3) lowest acceptable proposals, will be returned within fifteen (15) days after the time of opening the bids. The bid security accompanying the three lowest acceptable proposals may be held by Gaston County, North Carolina, until a construction contract has been executed and a satisfactory Performance Bond in the sum of the full amount of the contract has been delivered to Gaston County.

Each bid shall be accompanied by a letter from the bidder’s insurance representative acknowledging the insurance requirements as set forth in the General Conditions of the contract and its commitment to issue the required policies if awarded a Contract.

The award of any contract will be made by Gaston County, North Carolina, to the lowest responsive, responsible bidder. Responsible bidder will be defined as one who furnishes satisfactory evidence that he has the requisite experience and ability and that he has sufficient capital, facilities, and plant to enable him to perform the work successfully and promptly, and to complete the work within the time specified in the contract documents. At a minimum, responsible bidder shall be appropriately licensed by the State of North Carolina, have provided the required bid bond, have the capability of meeting bonding and insurance requirements, and be in compliance with Federal, State, and local laws and regulations applicable to the project.

Gaston County reserves the right to reject any proposal for failure to comply with all requirements of this notice or of any of the contract documents; however, it may waive any minor defects or informalities at its discretion. Gaston County further reserves the right to reject all proposals or award a contract which, in its judgment, is in the best interest of the County.

To download your package, click the “Place Order” link above and choose the package. There is no charge to download. Choose “None” for your payment method in the shopping cart. Your transaction will record you as an RFP recipient and will allow you to receive notification of any Addenda released during the RFP phase while it remains open. Downloads are not immediately available, you will receive an email when it is available.

Downloads do not include addenda, they are all available on the “Addenda” tab of this page.

ADDENDUM DISTRIBUTION

Plan holders will be notified by email when future addenda are issued and it will be the responsibility of the plan holder to download each addendum. If you would like a printed copy of an addenda please contact your local Duncan-Parnell office for this request. There is no cost to download or print the addenda. However, shipping, if required, will be charged.

Addenda notifications are sent via email from the mail account of “addendaNotification@dpibidroom.com” and could be flagged as spam by your company network firewall. To prevent not receiving timely notification of these addenda, please contact your company Information Technology Manager and ask that he “white list” the domain of dpibidroom.com to prevent emails from being captured.

If you need assistance navigating this site please contact Michaela Bruinius at michaela.bruinius@duncan-parnell.com

For Project Details Click Here

Details

Date:
October 18, 2022
Event Category:

Leave a Comment