ONWASA Dixon WTP Brine Tank Replacement

October 7

The project will consist of removing and replacing the existing brine tank #1 and connecting
to existing piping. The existing tank site glass and level control assembly will be reused on
the new brine tank. The new brine tank shall be completely automatic and self-contained
salt storage and salt dissolving unit for producing fully saturated brine from rock, solar or
evaporated salt products capable of producing 20 to 35 gallons per minute of saturated brine
flow under normal operating conditions. To minimize disruptions to ongoing plant operations,
the awarded Bidder shall procure and secure delivery of the tank prior to initiating any
construction activities on the project site. Due to the anticipated long lead time associated
with tank fabrication, the awarded Bidder shall proactively coordinate with ONWASA and
the Engineer to provide routine updates on procurement activities, manufacturing progress,
anticipated delivery dates, and schedule impacts to ensure alignment with the overall project
timeline. Upon delivery of the tank to the project site, ONWASA will accept and approve
payment for the tank, and the Contractor shall commence construction activities on the first
calendar day following delivery and shall diligently prosecute the Work to completion. All
Work shall be completed within ninety (90) consecutive calendar days following delivery of
the tank to the project site.