C.T. Wilson Construction invites you to apply for prequalification to bid on the City of Durham’s Environmental and Street Services South project at 1100 Martin Luther King Junior Parkway, Durham, NC.

Work will start in 2027 and end in 2028.

The project includes:

Phase 1:

  • warehouse supplies and shelving relocation
  • warehouse improvements including relocation of AC Unit and electrical.
  • demolition of three warehouse buildings and a shelter
  • site improvements

Phase 2:

  • construction of a two-story approximately 48,418 sqft office and warehouse building
  • a separate 2,300 sqft vehicle wash building
  • rock storage shelter

The project has LEED requirements and features including a geothermal system.

Available bid packages

Packages and estimated values are preliminary and subject to change.

Phase 1 — Warehouse Relocation, Demolition, and Sitework

Prequalification due: December 3, 2026, by 5:00 p.m. Eastern Time

Package Description Estimated Value
01A General Trades (includes mechanical and electrical) $170,625
02A Surveying $50,000
02B Demolition $545,248
31A Sitework $4,556,135

Phase 2 — Office and Warehouse Building and Vehicle Wash Building

Prequalification due: December 17, 2026, by 5:00 p.m. Eastern Time

Package Description Estimated Value
03A Concrete $844,644
04A Masonry $1,110,259
05A Structural Steel $2,326,979
06A General Trades $996,477
06B Architectural Woodwork $149,343
07A Waterproofing, Vapor Barrier, Sealants $309,338
07B Membrane Roofing $478,037
07C Wall Panels $638,875
08A Hollow Metal and Wood Doors, Frames and Hardware $331,936
08B Sectional Doors $135,346
08C Aluminum Storefront and Glazing $352,463
09A Gypsum Board Assemblies and Insulation $1,299,238
09B Tile $94,406
09C Acoustical Ceilings $161,912
09D Resilient Flooring $317,341
09E Fluid Applied Flooring $121,314
09F Exterior and Interior Painting $215,522
12A Window Treatments $56,160
14A Elevator $131,000
21A Fire Protection $213,252
22A Plumbing $760,000
23A Heating, Ventilating, Air Conditioning $4,646,000
26A Electrical, Communications, Fire Alarm $3,498,130
32B Fencing $130,000
32C Landscaping $129,735

Before you begin

Please gather the following documents and information before opening the application. You may need assistance from your accounting, insurance, or safety contacts. 

Supporting documents:

  • Most recent audited or reviewed financial statements.
  • Surety letter dated within the last 30 days showing single-project and aggregate bonding limits, if any selected package is $300,000 or more.
  • Certificate of insurance demonstrating the required coverage.
  • Insurance-carrier verification of up to five years of available EMR history, or documentation explaining why your company does not qualify for an EMR.
  • Applicable trade/general contractor licenses and NCSBE certification, if certified.
  • Resumes for the proposed superintendent and project manager.
  • Current, completed, and signed IRS Form W-9 matching the applicant’s legal entity name.

Information to enter:

  • Company, contact, business registration, and licensing information.
  • Annual billings for up to five completed fiscal years, current workload and remaining backlog, and the value of your largest completed project.
  • Applicable claims, litigation, bonding, and safety history.
  • Proposed project personnel and anticipated percentage of work performed with your own forces.
  • Three similar projects and three references for a single package; five projects and five references when applying for multiple packages. Have project descriptions, your company’s contract values, completion information, and reference contact details available.

Select each package for which your firm wishes to qualify and provide experience supporting each selected scope.

When you have the information, complete the online prequalification application at this link:

Durham Environmental and Street Services South Prequalification – Fill out form

The form does not accept file uploads. After submitting it, you will receive an email requesting supporting documents; reply to that email with the applicable attachments. Both the application and supporting documents must be received by the applicable phase due date. If applying for both phases, submit the information needed for Phase 1 by its earlier due date.

Details

Documents