- This bid has passed.
Neuse River Resource Recovery Facility BNR Basins MCC Replacement
The Project consists generally of the following major items:
• Demolition and in-kind replacement of MCC-P4B, MCC-P5B, and MCC-P6B.
• Demolition and replacement of PLC-81, PLC-82, and PLC-83 cabinets.
• New prefabricated metal enclosure with walls, roof, doors, lighting, and HVAC system to house new MCC and PLC.
• Extension of existing concrete foundation to accommodate new enclosure footprint.
• Demolition and replacement of all power wire cable within existing conduit from each MCC to each motor and device on BNR Aeration Basins 1-6.
• Demolition and replacement of sections of corroded electrical conduit from each MCC to each motor and device on BNR Aeration Basins 1-6.
We are requesting quotations for the following trades/disciplines:
SELECTIVE DEMOLITION
CONCRETE
METAL BUILDING
HAULING
ASPHALT PAVING
ELECTRICAL
CLEARING AND GRUBBING
FENCING
SCADA & CONTROL
EROSION CONTROL
GRASSING & SEEDING
PAINTING

