Project dates:
Date Due – Jun 1, 2023 at 11:00 AM PDT
Job Walk – May 16, 2023 at 12:00 PM PDT
RFIs Due – May 23, 2023 at 1:00 PM PDT
Expected Start – Jun 27, 2023
Expected Finish – Dec 29, 2023
Date Invited – May 10, 2023 at 12:52 PM PDT
General info
Project Name – NCSU Witherspoon Student Center First Floor Renovation, Phase 2
Location – 2810 Cates Avenue, Raleigh, NC 27606, United States of America
Project Size – 5,335 sq. ft.
Project Information –
The project consists of the renovation of portions of the first floor of Witherspoon Student Center including the Lobby, Men’s, and Women’s Rooms, and Room 126. A portion of room 126 and all of room 125 will have floor elevation raised to adjacent grade. The exterior patio outside of Room 126 will also be raised.
Phase 2: First Floor Renovation.
a. Commencement of Construction:
1) Start Date: On-site work of this phase shall commence by 6/27/2023.
b. Interim Milestones:
1) Renovation of Lobby 114A and Stair 114B shall be completed by 8/14/2023. If renovations in Lobby 114A and Stair 114B are not complete by 8/14/2023, any subsequent work must be completed after hours or on the weekends. After 8/14/2023, a clear, unobstructed path from the door leading out of the Theater to the Vestibule door must be maintained during normal business hours to provide egress from the Theater.
2) Renovation of Women 122 and Men 123 shall be completed by 10/11/2023.
c. Substantial Completion of Phase 2:
1) The renovation of Room 126 and the remainder of the work shall be completed by 12/29/2023
Phase 1 is a separate Fire Alarm project by others.