CT Wilson/ Student U Kitchen Renovation at WG Pearson Center

April 25, 2023

Project dates:
Date Due –  Dec 14, 2022 at 12:00 PM PST 
Job Walk –  Dec 1, 2022 at 7:00 AM PST
RFIs Due –  Dec 6, 2022 at 9:00 AM PST
Expected Start –  Feb 1, 2023
Expected Finish —
Date Invited –  Nov 22, 2022 at 12:01 PM PST
General info:
Project Name  – Student U Kitchen Renovation at WG Pearson Center
Location –  600 E Umstead St, Durham, NC 27701, United States of America
Project Size –  2,525 sq. ft.
Project Information –
The work consists of renovations to a former public school kitchen.
Project includes:
  1. Renovations to approximately 2,200 sqft of the interior kitchen, storage, and electrical/mechanical rooms.
  2. The addition of an 18’x18′ Outdoor Walk-In Freezer/Cooler and associated site work.
  3. Installation of a grease trap in the loading dock area with new connection to the sewer manhole in street.
  4. Installation of rooftop mechanical equipment including exhaust fans.
  5. Working around existing asbestos-containing wall plaster and window glazing.
 
C.T. Wilson is negotiating this project with the owner.
 
Please provide an alternate price for performance and payment bonds on work if proposal amount exceeds $100,000.
 
All subcontractors will have insurance that meets or exceeds the values in the certificate of insurance posted in the specs folder.
Related organizations
Architect –  DTW Architects

UPDATE:The 2017 Plans for this building are in the addendum folder for reference only. Pictures of the existing kitchen are also in the Files section. The cut sheets for the Armstrong Kitchen Zone ceiling panels are also in the addendum folder. Armstrong Kitchen Zone will be installed in the ceiling grid.

Student U Kitchen Renovations Addendum No_1.pdf

Student U Addendum No_2 – 4_13_2023.pdf